We have done some preliminary studies regarding traffic control through the corridor. It won’t necessarily be sequential from south to north, nor will it be done all at once.
There will be certain sections that are easier to work on because we do have to maintain two lanes of US 1 traffic through the corridor at all times, during high traffic times, peak hour times and sometimes during the daytime hours too.
So, it will be a little more patchwork. We will do it in as big of sections as possible to be convenient and more efficient for the contractor, but it won’t be all at the same time nor will it be sectioned south to north or north to south.