Based on our current level of progress with the environmental assessment, we will continue to develop the EA (Environmental Assessment) document through the summer and publish it this fall. We anticipate an environmental decision next summer of 2026 which at that time, assuming it’s a finding of no significant impact, we would shift into the final design / right-of-way acquisition phase of the project.
We anticipate that to start early in 2027. We anticipate that to take 18 to 24 months, which would put us in 2029 for a construction start. That’s based on where we are currently at. The construction would be anticipated to take 3 construction seasons or 3 years. We really have not gotten into detail on the construction schedule yet, but we are anticipating 3 construction seasons or 3 years.