1) Is it true there will not be an entrance/exit from Maple Ave/Route 1 anymore? 2) And is it true estimated start time 2027 and completion estimate 2029?

1) Maple Avenue interchange with US 1 will remain as it currently is. That was reconstructed in 2014 and will remain open also. We are just connecting that with an auxiliary lane which just essentially means it will be a weave lane between the 213 interchange and the 413 off ramp interchange. So, you would still enter Route 1 from 213, Maple Ave.

2) 2029 is the current anticipated construction start with a 3-year construction duration which would end in 2031.